Hoisted a total of 2.2 million pounds in 24 working hours while moving the crane 10 times.
Heaviest scrap turbine weighed 375,000#
4 turbines, 3 bottom casings and 3 top casings hoisted for demolition
Jarrell Contracting--Syndicate Trust building
176,000# of counterweight, 178' main boom & 219' luffing jib with 270' of hook height, hoisting 6000#unit at 235' radius
Beatrice Ethanol Plant—Beatrice, NE
Grove GMK7550 (550 ton ) crane to set a methanol column weighing 67,000 lbs at Beatrice Biodiesel plant in Beatrice, NE
The 135’ tall / 12’ diameter column had to be stood upright from the horizontal position using the 550 and a Manitowoc 10000 crawler as a tail crane.
The GMK7550 was configured with 132,000 cwt., 179.2’ of main boom and 59’ of fixed jib at a 3 degree offset.
AmeriStar Hotel & Casino
In essence the 550 acted as a mobile hydraulic tower crane, making picks for a variety of trades.
Working conditions were extremely tight requiring the 550 to work over another crane setting the pre-cast garage beams.
Crane was configured with the mega-wing attachment and 239.5’ of luffing jib, 179.2’ of main boom at 81 and 70 degrees, and 308,600 lbs counter weight.
Total radius with the configuration at 295` allowed Budrovich to pick a 6,850 pound hydro-mobile scaffold.
Hall Industrial—Hydraulic Press Relocation
Hoisted 265,000# hydraulic press after it had been previously dropped.
Partnered with Budrovich Excavating division to clean up site & prepare area for crane.
175' radius to hoist 8 demo towers and replace with six (6) new 8,000# towers.
Arranged all traffic control and street blocking permits.
Crane delivered on site and ready to make first pick in 4 hours.
Ameren UE—Meramec Unit #3 Shutdown
Alberici Constructors/Haberberger Mechanical
352,700 lbs of counterweight, 197' of main boom, the MegaWing lift attachment and 24' of Heavy Duty Jib at a 20 degree offset.
The vessel was lifted and replaced at a radius of 164'
Project pre-planning negated the new vessel needing to be shipped in pieces, moved into the location, welded together, heat treated, x-rayed and pressure tested at considerable cost and delay to the "shut down" window.
Original weight of old unit estimated to be 22,600#. Actual weight of old unit 32,000#
WUSM Hospital Parking Garage Tower Crane Disassembly
McCarthy Building
Challenging urban site with tight laydown; hospital Emergency Department in path of disassembly but must remain open; MetroLink rail tunnel running directly under configuration of GMK 7550
Vibrant communication plan implemented to coordinate the Helicopter Emergency Air Evacuation landing pad located on the adjacent building.
According to Fred Kern, Equipment Manager at McCarthy, “The 550 saved us two days of jacking and $15,000. I was amazed at how well it fit into a tight logistical situation.” Budrovich and McCarthy decided to utilize the GMK , as its capacity and reach would save two days of jacking the tower crane down to the point where a GMK 6350 could disassemble the Liebherr 550HC20.
GMK7550 550 ton mobile hydraulic crane providing hoisting services to industrial, commercial, and civil construction companies.